In response to questions from RTÉ's Prime Time, the local authority said it expects the tea rooms could be operational in May or June 2027.

The facility was originally due to be completed by the end of 2024. The project, budgeted at €2.4 million in 2018, is now costing more than €6m.

The Merrion Square tea rooms, in development since 2015, will have a café with an outdoor terrace facing into the park. The building will have public toilets and a foyer, which can act as an exhibition space.

Improvements are also being made to the pavements and public lighting.

The council had earlier put the potential final cost at as much as €7.5m, though it now says it does not anticipate the bill reaching that figure.

"It's the most expensive tea room in the history of the State," Independent Councillor Mannix Flynn said.

"We're not in a crisis of tea, we're in a crisis of housing and while I can't get a window fixed in a block of flats, Dublin City Council seems to be able to come up willy-nilly with millions for unnecessary tea rooms."

Despite the rising costs, the local authority confirmed to Prime Time that the building is 20% smaller than originally designed. Reducing the footprint from 371 sq.m to 292 sq.m saved money, but not enough to keep the budget down.

DCC said the tea room's costs reflected the "cumulative impact of Covid, extended programme duration, construction inflation, statutory compliance requirements, contractual disputes and associated delay costs over the period of the project."

Construction by main contractor Bracegrade was delayed by 18 months as a result of the contractual dispute.

Work resumed earlier this year following mediation with the contractor and the design team, but the tea room's completion has been pushed back to next spring.

"The contractor has provided a date of March/April 2027 for the completion of construction and fit out works. It is anticipated that the operator could have the pavilion open to the public in May/June 2027," it said in a statement.

Tea rooms are one way to provide supervised public toilets, and there are ten such facilities in Dublin city parks. But Fine Gael Councillor Danny Byrne called the Merrion Square project excessive.

"It's huge money for a tea room, a public toilet and some artist space."

While councillors voted in favour of the building at the planning stage, members did not support "runaway costs," he said.

"There seems to be a disregard for the taxpayers' money. It works very differently in the private sector but when there's public money it seems to be an unlimited amount."

The rising project costs include design fees payable to architects Bucholz McEvoy, which grew from €246,000 in 2015 to €655,000 in recent years. The increase was noted by the Local Government Audit Service in its 2024 audit of DCC.

The local authority said the fee was as a result of scope changes, delays and inflation, adding it was a percentage which is "broadly in line with current industry design team fees scale for a building of this value and complexity."

However, it acknowledged that the project did not fully comply with the procurement regulations that apply to the local authority.

Cllr Byrne said documents released to him under Freedom of Information show the local authority's own internal project watchdog - the Corporate Project Governance Board - suspended the project in 2019 over the scope and cost. But it was restarted the following year.

"Seven years ago, the council’s own governance board was questioning the costs and the business case. Seven years later I’m still looking for answers," Cllr Byrne said.

The documents also show among the cost overruns and delays were issues relating to the square’s trees which emerged following the inspection of tree roots by an arborist.

In response to councillor disquiet, the local authority announced it would appoint an external consultant to undertake a review of the project.

It will assess the "extent and causes of cost overruns and schedule delays," along with examining the "effectiveness of project governance, reporting and decision-making arrangements," members were told.

Merrion Square is in Dublin's south Georgian quarter and is visited by up to a million visitors each year. A Conservation and Management Plan for the square was published by the council in 2014 which identified the need for a tea rooms and public toilets in the park.

The building, which is located near the playground and Oscar Wilde statue, is designed to slope from the street into the park.

In planning documents architects said the tea room would "touch the ground lightly," with minimal impact on the surrounding trees and the ground beneath.

The structure has stone cladding to the north, timber and glazing to the south and is built under a canopy of trees, some 200 years-old.

"Merrion Square is one of the great architectural set pieces of Georgian Dublin and its park is the heart of the square," Donough Cahill, Executive Director of the Irish Georgian Society said.

There is merit in constructing an architecturally beautiful building to enhance the environment, he argued.

"Trying to achieve that standard of excellence is something that's very understandable. The scaling of the building is very important, that it's not going to be intrusive or compromise its surroundings."

Mr Cahill noted that there have been increased efforts to host events in Merrion Square in recent years to bring life to the space.

But Councillor Flynn maintained the tea room was a "vanity project", questioning the expenditure in the context of increasing rents being charged to local authority tenants.

"I want a good building, I want good architecture, I'm an artist myself, but not at this expense. We need houses, we need accommodation, we don't need tea rooms," he said.

A report on the Merrion Square tea rooms from Louise Byrne and producer/director Isabel Perceval is broadcast on 24 November edition of Prime Time on RTÉ One and RTÉ Player.