Strict new grid connection standards for power-hungry data centres mean developers will need to have fault ride-through and super-fast voltage control capabilities “active, modelled and compliant” before their site can be energised, in a rule change that could prove to be a boon for big batteries.

New energy market rules are being set to govern how data centres connect to and behave on Australia’s electricity grid, in a bid to prevent incidents like the 1,500 megawatts (MW) of simultaneous disconnections that struck the US state of Virginia two years ago.

The Australian Energy Market Operator (AEMO) last week published its Interim Guideline, seeking feedback on early measures while new and updated technical guidelines are developed in line with new rules published earlier this month.

A final determination on Improving the NEM Access Standards – Package 2 was published on November 12 by the Australian Energy Market Commission (AEMC), setting out new rules and requirements for inverter-based loads above 30 MW, as well as for AEMO to manage them.

At the time, AEMC chair Anna Collyer said the newly strengthened rules would, in particular, govern the increasing number of large data centres connecting to the grid, with demand from the AI processing factories forecast to grow sevenfold, from 5 to 34 terawatt-hours (TWh) by 2035.

“Our guiding principle is that once a customer is big enough to materially affect the grid, it must be treated as part of that grid,” Collyer said.

“Our reforms will also ensure new data centre connections can proceed efficiently and securely, without unexpected costs or risks being pushed onto other electricity consumers.”

As the AEMC notes, data centres often use sophisticated electronics that can respond quickly to changes in the grid, but the July 2024 incident in Virginia in the US that resulted in 1,500 MW of simultaneous disconnections stands as a stark example of how things can go wrong.

To address this risk, the AEMC’s final rule introduces a “clear 30 megawatt (MW) threshold” for large inverter-based loads, including data centres, that among other things requires them to ride through power system disturbances, rather than disconnecting when the system is under stress.

The new rules also require network businesses to consider the combined impact of nearby large inverter-based loads, recognising that several connections can interact with each other and have a greater collective impact than an individual connection.

For AEMO’s part, the market operator is required to develop “clear modelling guidance for large loads, with requirements designed to be proportionate to the potential impact of a connection and practical for industry to implement.”

To this end, AEMO last week published its Interim Guideline for Connection of Inverter Based Loads (IBLs), to set data centres and others on the right track ahead of the full implementation of updated technical guidelines – which is required to be in place within 12 months of the AEMC’s final rule.

Grid-scale energy storage heavyweight, Fluence, says the delivery of draft modelling guidelines by AEMO so soon after the AEMC’s final rule has been an encouraging sign that the potential problem of a data centre rush to the grid is being dealt with quickly and collaboratively by the powers that be.

“I think it’s just a really good thing to see that, in the midst of a million different policies going on for data centres, the AEMC and AEMO were quite coordinated in this approach, and they’ve been really clear and fast in their guidance to industry,” Fluence Energy’s senior manager of policy and strategy, Sam Markham, told Renew Economy this week.

“It is highly encouraging to see our market bodies coordinating to deliver clear, consistent, and detailed advice,” Markham added in an emailed statement.

“While these reforms establish important new obligations for facilities to support grid security, they also preserve a realistic connection pathway. This level of coordination gives developers the practical certainty they need to get straight to work when speed-to-market is everything.”

Fluence, a joint venture between Siemens and AES that has become a global leader in utility-scale battery storage, says the updated requirements for new data centres also puts batteries in the frame as one of the best and quickest ways to comply with the new standards.

Markham says the new rules represent a major shift that is accelerating behind-the-meter (BTM) “parallel battery deployment” to protect data centre developer energisation timelines, ensure reliable energy supply and meet grid connection obligations.

“As data centres scale to become major pillars of our digital infrastructure, treating them as active, resilient participants in the electricity grid is a necessity,” Markham said. “Meeting these strict requirements for frequency and voltage ride-through demands proven, grid-forming technology.

“The AEMC has been really flexible, intentionally, so that … innovation can come in [and] different technologies can provide different types of solutions.

“[But] you still need something that can do the really, really, really fast millisecond response,” she tells Renew Economy. “So there is potentially super powered response stuff within a data centre, already, that might be able to do some of that.

“The solution that we’re proposing is basically [that] an energy storage system, like a standalone battery, can support a data centre behind the meter and provide a lot of these services.

“For developers, this means they can meet strict grid-forming and ride-through performance requirements without compromising tenant Power Usage Effectiveness (PUE) or delaying project energisation.”

Crucially, Markham adds, it also means operators can no longer stage battery storage (BESS) as a later addition – rather, the rules require grid-support technology to be active, modelled, and compliant on day one.

“There is a bit of nuance in the rules where, for things like short circuit ratio withstand … that can be contracted later, as long as there is a contracted relationship that AEMO can see,” she says.

“But on the whole … when you negotiate your [grid] access standard to connect a new data centre now, you need to have all the bits that would be required for you to deliver on that access standard.

“So from day one, you need to be able to ride through faults and do these other things,” Markham says.

AEMO says stakeholders are encouraged to provide feedback on its interim guidelines by December 17, to help inform the next update, planned for January 2027. A webinar on December 2 aims to further explain the Interim Guideline and consultation process and answer questions.

For the AEMC’s part, the final rule for Improving the NEM access standards – Package 2 is effective immediately. But it says applicants who are advanced in the connection process and have negotiated their access standards will be given a 6-month grace period to finalise their connection.

“This allows connection applicants who are close to finalising negotiations with their Network Service Provider to use the old access standards, to minimise disruption to their applications,” it says. For more information about the new rule, visit the AEMC’s project page .

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter .

If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Please click here. Your support is invaluable.

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share on Facebook (Opens in new window) Facebook

Share on X (Opens in new window) X

Share on LinkedIn (Opens in new window) LinkedIn

Share on Reddit (Opens in new window) Reddit

Email a link to a friend (Opens in new window) Email

Print (Opens in new window) Print

Strict new grid connection rules for data centres could provide inside running for big battery projects

Data centres will need to have fault ride-through and ultra-fast voltage control “active, modelled and compliant” before they can be energised.

Andrew Forrest’s Squadron Energy proposes Australia’s biggest battery – up to 8,000 MWh – west of Sydney

Andrew Forrest’s Squadron Energy unveils plans for Australia’s biggest battery – with nearly 70 times the storage of the original Tesla big battery.

Host of giant PV and battery hybrid project wants to sell – and the solar lease is now the big sales pitch

A host of almost a third of the land of one of the country’s biggest solar and battery hybrid projects wants out, and institutions could be the buyer.

Australia missing big opportunity in battery manufacturing, despite having all the minerals

Australia is missing opportunity to create a thriving battery manufacturing industry because it exports critical minerals rather than turning them into high-value products.

Jennifer Dudley-Nicholson

Join our WhatsApp Channel

I allow to create an account

When you login first time using a Social Login button, we collect your account public profile information shared by Social Login provider, based on your privacy settings. We also get your email address to automatically create an account for you in our website. Once your account is created, you’ll be logged-in to this account.

Please login or register to comment

Plan to build big battery in ex-premier’s home town will have to dodge abandoned gold mine shafts

Coal power offers “no chance to compete,” says Rio Tinto, as smelters go all-in on renewables

“Deniers and delayers:” Bowen marks 600,000 cheaper home batteries, but says balcony solar cannot be rushed

State adds $4,000 “discount” to energy upgrade scheme, targeting low-income households and renters

“Unbankable:” Fresh blow to Beetaloo as last of Big Four banks rules out finance for new gas pipelines

The Driven Podcast: Australia’s EV discount under threat as more Chinese EV brands arrive

The Driven Podcast

The line that Australia’s nuclear power ban was never properly debated is, frankly, bullshit

After COP31 letdown, the worst thing Albanese can do now is to sound retreat on EVs, batteries and housing