Hobart's Macquarie Point stadium and precinct costs rise to $1.54 billion
By state political reporter Josh Duggan
Topic: Infrastructure Construction Industry
Posted Tue 24 Nov 2026 at 8:31am Tue 24 Nov 2026 at 8:31am Tue 24 Nov 2026 at 8:31am , updated Tue 24 Nov 2026 at 11:27am Tue 24 Nov 2026 at 11:27am Tue 24 Nov 2026 at 11:27am
The Tasmanian government says the cost of building the Macquarie Point stadium will be $1.23 billion, up from last year's estimate of $1.13 billion.
When "project costs" and precinct infrastructure including a car park and power supply are included, it rises to $1.545 billion.
The premier says the stadium and its new cost will not be headed back to parliament for approval.
The total estimated cost of the Macquarie Point stadium precinct has risen to $1.54 billion, the Tasmanian government has revealed.
The 23,000-seat roofed stadium, which is a condition of Tasmania's AFL deal, was approved by the Tasmanian parliament last December.
A new estimate revealed today has put the cost of stadium delivery at $1.23 billion.
But that figure does not include the wider precinct infrastructure costs needed to support the project that the government also announced today.
A car park and power supply for the precinct was budgeted at $132 million, while project delivery costs add another $183 million.
This brings the total to $1.54 billion.
Contingency costs not included
There is also a "client contingency" amount, which has not been revealed or included in costs.
It will cover any potential rise though the final stage of procurement negotiations and, if needed, would bring the project cost even higher.
Until today, the most recent stadium cost estimate had been from September, when the government priced the stadium at $1.13 billion, however this figure included project costs and contingencies.
Last week, the lower house of the Tasmanian parliament passed a motion calling for the "current estimated cost" of both "stadium delivery", and "the broader Macquarie Point precinct-enabling infrastructure", including power upgrades and a centralised car park.
In order to win over the votes needed for the approval order to pass the Legislative Council, the government made a number of commitments, including to limit the state's contribution to $875 million.
Treasurer and Minister for Macquarie Point Urban Renewal Eric Abetz said the government would cover the shortfall from state funds, breaking the promised state contribution cap.
He said the state would then "look to what opportunities there are to gather the funding, and as a result reduce the borrowings that are necessary".
Parliament grills government on costs
In parliament this morning, Tasmanian Greens leader Rosalie Woodruff asked Mr Rockliff if he would keep his promise of a $875 million taxpayer funding cap.
Mr Rockliff responded that the spending cap "was the best estimate at the time".
"I couldn't foresee the conflict in Iran," he said.
"I acknowledge we have to borrow more to see the project through, and we had the best estimate back in September last year so now we're 14 months on with the Iran conflict and cost escalation in everything we do."
Ms Woodruff asked Mr Rockliff if there was "any limit to how much you're prepared to spend or commit of Tasmanians' taxpayer money to get the stadium built".
He did not answer the question, instead saying the government had been "up-front with the Tasmanian people".
The federal government has committed $240 million to the Macquarie Point precinct, and the AFL is chipping in $15 million for the stadium.
Despite the US–Iran war pushing up construction costs worldwide, the government has only recently admitted the stadium would likely cost more than estimated last year.
Independent Clark MP Kristie Johnston asked Mr Abetz whether the government had calculated what the loan financing would cost.
"How much interest will we be paying on the stadium borrowings over the next 10 years?" she said.
But Mr Abetz criticised Ms Johnston and "those that have opposed the stadium each and every step of the way".
"Have you written to federal Labor, have you written to the AFL, have you written to Cricket Australia asking them to make a bigger contribution for the stadium so our borrowings may be less?"