Can Future Generations Sustain It?
Snowy 2.0, government cost blowouts, Australian sovereignty and Dan Duggan
If governments can underestimate the cost of one major infrastructure project by more than tenfold, what confidence should taxpayers have in Australia’s largest and most complicated defence commitment?
A familiar Australian problem
There is a recurring problem with major government projects in Australia. They are often announced with impressive promises, attractive initial budgets and assurances that the financial risks have been carefully assessed. Yet once construction begins and time passes, our memories tend to fade while the costs usually skyrocket. Of course, by then we are consumed with many other concerns, like feeding the family and paying the mortgage.
Design changes, engineering difficulties, contractual disputes, labour shortages, inflation and delays can turn what initially appeared to be manageable projects into enormous financial liabilities.
Snowy 2.0 is now one of the most striking examples.
Announced in 2017 with an estimated cost of approximately $2 billion, the pumped-hydro project was promoted as an important component of Australia’s future energy system. It was intended to provide large-scale energy storage by moving water between two reservoirs and generating electricity when required.
However, the latest reassessment has placed the target cost to complete at $22.2 billion, with Snowy Hydro allowing for a possible $25 billion scenario.
The $25 billion scenario represents 12.5 times the original estimate, an increase of 1,150 per cent.
The expected commissioning date has also moved to late 2029, compared with the original expectation of completion in 2021.
Snowy Hydro and the Government have identified several contributing factors, including design immaturity at the original investment decision, difficult geological conditions and escalating construction costs.
Whatever the explanations, the financial outcome is extraordinary. A project originally presented as a $2 billion undertaking has become a potential $25 billion liability, and it is not yet finished.
What energy experts have been saying
Professor Bruce Mountain, Director of Victoria University’s Energy Policy Centre, and energy expert Ted Woodley have raised serious questions about Snowy 2.0.
In their criticism, the fundamental concern is that the project was seriously underestimated from the beginning. The engineering challenges, enormous construction costs and rapid development of alternative battery technology all raise questions about whether such a complicated project represents good value for money.
Mountain and Woodley have also questioned the economic justification for relying on a massive pumped-hydro project when alternative storage technologies are becoming increasingly competitive.
Read: Professor Bruce Mountain – Pushing water uphill: The issues with Snowy 2.0
The energy lost in pumping water uphill
There is a fundamental issue with pumped-hydro storage that deserves greater public attention.
Snowy 2.0 is an energy-storage system, not a source of new energy. Electricity is required to pump water uphill into the upper reservoir. When that water is released and flows back down through the turbines, electricity is generated, but some of the original energy is lost in the process.
Consequently, the system must consume more electricity pumping water uphill than it subsequently returns through generation.
The important question is whether the value of the electricity returned justifies the enormous construction costs, operating expenses and energy losses involved.
Bruce Mountain – The practical limitations
Professor Mountain has also questioned whether Snowy 2.0 can deliver the enormous storage capacity claimed for it in practice.
One particular concern is that the upper reservoir does not have an independent water supply sufficient to sustain prolonged generation. Once the water has been released, it must be pumped uphill again. This depends on having sufficient water available in the lower reservoir and access to electricity at an economical price.
In an ABC report published on 31 October 2026, Mountain questioned the practical usefulness of the advertised ability to generate electricity continuously for approximately a week.
This raises legitimate questions about how much of the project’s advertised storage capacity can realistically be relied upon under actual operating conditions.
Read: ABC News – Does Snowy 2.0 still have a place as batteries reshape Australia’s power grid?
The Spirit of Tasmania provides another warning
Snowy 2.0 is not the only Australian infrastructure project to demonstrate how dramatically government project costs can escalate beyond their original estimates.
The replacement of Tasmania’s two Spirit of Tasmania ferries provides another concerning example of inadequate project planning, delays and escalating costs.
The programme, which began in 2017–18, involved replacing the existing passenger ferries with two larger vessels built in Finland, together with the construction of upgraded berthing facilities at Devonport.
The original Devonport berth estimate was just $90 million. By May 2026, the revised budget had reached $493 million.
That represents an increase of $403 million, or approximately 448 per cent. In other words, the berth project is now expected to cost almost five and a half times its original estimate.
The two new ferries have also experienced substantial additional costs. According to figures presented to Tasmania’s Parliamentary Public Accounts Committee, the vessels incurred approximately $280 million in additional costs, attributed to changes in shipbuilder, contractual adjustments, the Russia–Ukraine war and financial support for the Finnish shipbuilder.
The additional costs were broken down as follows:
Devonport berth facilities: $90 million originally, rising to $493 million – 448% increase.
Two replacement vessels: approximately $280 million in additional costs.
Geelong terminal: a further $34 million associated with changes to the project scope.
In May 2026, TT-Line chairman Ken Kanofski told the parliamentary inquiry that the combined cost overrun for the vessel replacement and two berths was approximately $717 million.
This figure relates to capital costs alone. It does not include the full additional expense of keeping the new vessels in temporary berths in Scotland and Victoria while the Devonport facilities were being completed.
The consequences have extended beyond construction costs. The Tasmanian Government subsequently announced a $506 million financial injection for TT-Line, while the company’s borrowing capacity was increased.
The new vessels were also years behind their original delivery schedule, with the replacement programme initially anticipating the ships entering service in 2021.
There is an important lesson here. Even a relatively straightforward ferry replacement programme, involving established international shipbuilders and conventional marine infrastructure, can encounter extraordinary financial difficulties when project management, contractual arrangements, construction schedules and supporting infrastructure are not properly coordinated.
A ferry replacement programme is obviously not comparable in technical complexity to Australia’s proposed nuclear submarine programme. However, the financial risks associated with international contracts, overseas manufacturing, supply-chain disruptions, changing requirements and construction delays are directly relevant.
If a project of this scale can accumulate $717 million in additional costs, Australians are entitled to ask how effectively the much larger and more complex AUKUS submarine programme will be managed over several decades.
ABC News – Spirit of Tasmania replacement programme $717 million over budget, 12 May 2026
Tasmanian Parliamentary Public Accounts Committee – Spirit of Tasmania project inquiry
AUKUS: a much larger financial exposure
The Australian Government’s published estimate for the nuclear-powered submarine programme is between $268 billion and $368 billion over several decades.
The upper estimate already includes approximately $123 billion in contingency provisions intended to accommodate unforeseen events and risks. This contingency must not be added to the $368 billion a second time.
Nevertheless, the financial commitment is enormous.
Unlike a conventional infrastructure project, AUKUS involves much more than purchasing submarines. Australia must develop supporting infrastructure, train and maintain specialist personnel, establish the regulatory framework for nuclear-powered vessels and acquire the capability to operate and maintain nuclear submarines over their service lives.
There will also be substantial long-term obligations associated with maintenance, upgrades, nuclear stewardship and eventual decommissioning.
The public needs a clear understanding of what is included in the published estimates and what additional liabilities may emerge over the programme’s lifetime. Even relatively modest increases beyond the existing upper estimate would have significant consequences.
A 20 per cent increase would take the $368 billion figure to approximately $441.6 billion. A 50 per cent increase would take it to $552 billion. A doubling would produce a figure of $736 billion.
These are illustrations of possible cost escalation, not official forecasts.
The American submarine production problem
Perhaps one of the most significant concerns is that Australia is relying on the United States to deliver submarines while the American shipbuilding industry is already struggling to meet its own production targets.
Under the AUKUS arrangement, Australia is expected to acquire Virginia-class submarines from the United States before the planned introduction of the British-designed SSN-AUKUS submarines.
However, the American industrial base faces substantial difficulties expanding production. A Congressional Research Service review reported that Virginia-class submarine production had been running at approximately 1.1 to 1.2 submarines annually during the period examined, well below the US Navy’s planned rate of two per year.
There is also a backlog of submarines ordered but not yet delivered.
This raises an obvious question: if the United States cannot currently manufacture submarines at the rate required to satisfy its own naval programme, how confident can Australia be that it will receive the vessels promised under AUKUS on schedule?
Australia is not simply purchasing a finished product from an established supplier with unlimited manufacturing capacity. It is depending on another country’s ability to expand a highly specialised industrial sector while meeting its own strategic requirements.
Any delays or changes in American priorities could have direct consequences for Australia’s submarine programme. The same concerns apply to Britain’s ability to develop and deliver the next generation of submarines.
What the AUKUS Public Inquiry has raised
The financial questions are not the only concerns surrounding AUKUS.
The Australian Peace and Security Forum’s independent AUKUS Public Inquiry, whose commissioners included former Chief of the Defence Force Admiral Chris Barrie, examined whether the agreement would genuinely improve Australia’s security and whether its central submarine commitments were achievable.
Its report, Surrendering Australia : The AUKUS Deception , raised serious questions about the programme’s delivery timetable, Australia’s dependence on American and British industrial capacity and the consequences for Australian sovereignty.
The inquiry questioned whether the proposed delivery schedules for the three Virginia-class submarines and the future SSN-AUKUS boats were realistic.
It also raised concerns about the prospect of the Australian Defence Force having to manage and crew three different submarine types during the transition.
These are significant operational and workforce challenges, not simply accounting issues.
The inquiry also examined the circumstances surrounding the original agreement.
AUKUS was announced in September 2021 by then Prime Minister Scott Morrison, alongside US President Joe Biden and British Prime Minister Boris Johnson.
The agreement was negotiated without a comprehensive public parliamentary inquiry beforehand, and subsequent decisions concerning the programme’s financial commitments and implementation have attracted criticism over the level of public and parliamentary scrutiny.
The inquiry argued that Australians had not been given adequate answers to fundamental questions about the costs, risks and strategic consequences.
These criticisms deserve serious consideration, particularly given the scale of Taxpayers money involved.
Pillar II: another financial question
AUKUS also includes a second component, known as Pillar II, involving cooperation in advanced military technologies.
This covers areas such as artificial intelligence, autonomous systems, quantum technologies, advanced materials and hypersonic weapons.
However, the AUKUS Public Inquiry raised concerns that Pillar II remains uncosted and questioned whether the arrangements provide sufficient protection for Australian intellectual property and national interests.
This creates another problem for taxpayers.
If the submarine programme already represents a commitment of hundreds of billions of dollars, what additional financial obligations could arise from the technology-sharing arrangements?
It is difficult to assess the true financial exposure of a programme when important components have not been fully costed.
The public should not have to wait until further commitments are made before learning what they might eventually cost.
Dan Duggan: when AUKUS intersects with Australian sovereignty
There is another dimension to Australia’s relationship with Washington that deserves attention, and it concerns an Australian citizen who has spent more than four years in maximum-security detention fighting extradition to the United States.
Dan Duggan is a former US Marine Corps fighter pilot who moved to Australia in 2002, married an Australian woman and became an Australian citizen on 26 January 2012. In doing so, he relinquished his US citizenship. He is a husband and father of six children.
He was arrested by the Australian Federal Police on 21 October 2022 and has remained imprisoned in Australia while fighting extradition, despite never having been charged with an offence in Australia.
One particularly significant statement appears in records from the Attorney-General’s Department:
“The AFP, who is the appropriate law enforcement agency with responsibility for investigation of the types of offences for which Mr Duggan is accused, has confirmed that it did not identify any Australian offending, nor commence any investigation into Mr Duggan.”
This is an extraordinary statement from an Australian Government department. The AFP confirmed that it identified no Australian offending and commenced no investigation into Duggan. Yet Australia has continued to detain one of its own citizens on behalf of a foreign government for more than four years.
The case raises an uncomfortable question about the practical meaning of Australian citizenship when the interests of a powerful ally are involved.
Jessica Lewis and the September 2023 Senate hearing
There is a particularly interesting connection between Dan Duggan’s extradition and the AUKUS partnership.
On 6 September 2023, the US Senate Foreign Relations Committee held a hearing entitled AUKUS: A Generational Opportunity to Deepen Our Security Partnerships with Australia and the United Kingdom .
One of the witnesses was Jessica Lewis, then US Assistant Secretary of State for Political-Military Affairs. During the hearing, the issue of Chinese pilot training and the protection of American military technology was raised. Lewis responded by referring to an Australian pilot she had learned about during a visit to Australia.
“While I was in Australia, I did learn that an Australian pilot also participated, and we’re looking to extradite that pilot here under our laws to deal with that issue.”
Lewis did not name Duggan, but the circumstances clearly point to his case.
What makes this exchange particularly significant is that it occurred during a Senate hearing specifically examining the AUKUS partnership, including the sharing of sensitive military technology and the alignment of Australian and British export-control arrangements with American standards.
The exchange raises legitimate questions about the relationship between Australia’s defence commitments and its handling of an Australian citizen sought by the United States.
Imagine the difference in treatment of Duggan if it were China seeking his extradition. Our fearless leaders would be screaming from the rooftops, as would our media.
It does not establish that Dan Duggan’s extradition was negotiated as part of AUKUS, or that any agreement was made to exchange cooperation on one matter for cooperation on another. There is no established evidence of such a bargain.
However, the timing and circumstances warrant scrutiny.
Why was an American official discussing the extradition of an Australian citizen in the middle of a Senate hearing about deepening defence cooperation with Australia?
And what consideration did the Australian Government give to its own citizen’s rights and interests while negotiating an increasingly close defence relationship with Washington?
These are legitimate questions that deserve answers.
The trillion-dollar question
This brings me to a calculation that I believe deserves consideration.
Snowy 2.0 has increased from an original estimate of $2 billion to a possible $25 billion. That is a 12.5-fold increase.
If we were to apply that same multiplier to the approximately $367.6 billion AUKUS upper estimate, the resulting figure would be approximately $4.6 trillion.
I want to make clear that I am not suggesting AUKUS will necessarily experience the same percentage increase as Snowy 2.0; it could be more. The projects are entirely different in nature, scale and complexity. Nor am I presenting $4.6 trillion as an official estimate. History has shown me that the bigger the project, the greater the chance of a bigger blowout. Time will tell.
Some might dismiss such a figure as excessive speculation. However, I would argue that the extraordinary cost escalation of Snowy 2.0 demonstrates why Australians should not automatically accept initial government estimates as reliable indicators of the eventual bill.
If governments can underestimate a major infrastructure project by such an extraordinary margin, why should taxpayers accept assurances that a much larger and more complicated international defence programme will remain within its current budget?
I believe this is a perfectly legitimate question.
What else could Australia do with the money?
There is another aspect of this debate that receives insufficient attention: opportunity cost.
Every dollar committed to AUKUS is a dollar that cannot simultaneously be spent elsewhere.
Australia faces significant challenges involving housing affordability, healthcare, aged care, education, transport infrastructure, energy security and declining domestic manufacturing capability.