Transgrid will build and operate the transmission line that will link New South Wales’ (NSW) new energy heartlands with its coastal industrial hubs.

Four months after the NSW government gave its planning green light to the 110 km Hunter transmission project, it’s opened the way for construction to start next year.

It will close a critical gap in the state’s electricity network, created by the exit of its ageing coal-fired power stations, by linking the Central-West Orana and New England renewable energy zones REZ with coastal industrial hubs and cities.

Engineering firms Downer EDI and UGL will handle the transmission and substations, respectively.

Downer says its contract is worth $1.1 billion to build the 110 kilometres of new double circuit 500 kilovolt (kV) transmission line and the towers from the Bayswater South switching station in the Upper Hunter to the Olney station in the Lower Hunter.

This will replace existing transmission lines that lack the capacity needed to transfer electricity from the state’s proposed renewable energy zones to consumers.

Transgrid is also responsible for delivering the Humelink transmission line and the ill-fated Project Energy Connect link to South Australia — a project where costs blew out by more than $1 billion . It has already started work on the NSW section of VNI West, the Victorian interconnector the state Coalition has vowed to cancel.

Little private land

What the new transmission isn’t needed for is to open up the Hunter REZ, which is being built around the existing power lines that serviced the valley’s coal-fired power stations.

And in a critical difference to some of Australia’s most controversial transmission lines, such as Victoria’s VNI West, the Hunter line cut the number of private properties needed from 70 to 20 and stuck to mining, energy and government-owned land.

Transgrid CEO Brett Redman says they will still be working with Hunter Valley communities as they build the project “in a responsible way and provide social and economic benefits that leave a lasting legacy for the region.”

“EnergyCo has been an important partner in enabling this kind of infrastructure to be developed,” he said in a statement. “Our focus now is on delivering this essential transmission infrastructure safely and efficiently for the NSW government as the state transitions to a more reliable, secure and affordable energy future.”

The project is expected to create 900 jobs during construction and tap the existing talent and workforce already in the Hunter Valley.

Planning approval included 115 conditions to protect the environment, manage construction impacts, support landowners and ensure ongoing engagement with communities throughout delivery.

EnergyCo chief Hannah McCaughey says the latest award is a major milestone for the project.

“This is a critical piece of infrastructure that will increase the capacity of the electricity network and help unlock new renewable generation and storage,” she said in a statement.

Transmission has become a major pressure point for the transition from fossil fuel to renewable-powered electricity.

Groups across Victoria and NSW are opposing the critical infrastructure on the grounds that towers are an eyesore, debunked claims they may either start fires or making fighting fires impossible, and that farming can’t happen underneath, among other claims.

In South Australia, landowners along the proposed Northern Transmission Project that will link the state’s wind and solar heartlands to its capital, Adelaide, and NSW, are demanding clarity on what living with transmission towers means for farming.

In Victoria, some landowners have gone so far as to prevent employees of Vicgrid, the state’s network manager, onto their land and incurred significant fines in the process.

This level of commitment to opposing transmission lines is yet to be seen in other states, which also fine landowners who refuse to work with transmission companies.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share on Facebook (Opens in new window) Facebook

Share on X (Opens in new window) X

Share on LinkedIn (Opens in new window) LinkedIn

Share on Reddit (Opens in new window) Reddit

Email a link to a friend (Opens in new window) Email

Print (Opens in new window) Print

EnergyCo , NSW , Transgrid , Transmission

State awards contract to build major new transmission link, from old coal to new energy

EnergyCo names the winner of the contract to build and operate the transmission line that will link state’s new energy heartland with its coastal industrial hubs.

Rooftop solar ban to continue as network races to replace new towers blown down by “once-in-2,000 year” storm

Ban on rooftop solar exports to continue as authorities seek answers as to how and why newly installed transmission towers collapsed in face of fierce storm.

Not reliable, not affordable: Report shows ageing coal plants boost blackout risk, push up prices

New analysis shows Australia’s ageing coal-fired power stations are raising the risk of blackouts and higher electricity prices and should be phased out.

Jennifer Dudley-Nicholson

After COP31 letdown, the worst thing Albanese can do now is to sound retreat on EVs, batteries and housing

Disappointment in Antalya comes as PM mulls reverse on key climate policies. But, just like the PM’s retreat on indigenous policies, it would be a generational error.

Join our WhatsApp Channel

I allow to create an account

When you login first time using a Social Login button, we collect your account public profile information shared by Social Login provider, based on your privacy settings. We also get your email address to automatically create an account for you in our website. Once your account is created, you’ll be logged-in to this account.

Please login or register to comment

Plan to build big battery in ex-premier’s home town will have to dodge abandoned gold mine shafts

Coal power offers “no chance to compete,” says Rio Tinto, as smelters go all-in on renewables

“Deniers and delayers:” Bowen marks 600,000 cheaper home batteries, but says balcony solar cannot be rushed

State adds $4,000 “discount” to energy upgrade scheme, targeting low-income households and renters

“Unbankable:” Fresh blow to Beetaloo as last of Big Four banks rules out finance for new gas pipelines

Energy Insiders Podcast: On the ground at COP31

Energy Insiders Podcast

EVs are getting better – the real-world tests show it. Now we just need chargers to catch up