A batch of “tall, shiny poles” being installed at the Wooreen Energy Storage System in Victoria’s Latrobe Valley have been confirmed as lighting rods, not lighting poles, hopefully putting the concerns of some locals to rest.

EnergyAustralia, one of Australia’s “Big 3” gentailers, posted to its LinkedIn account last week a clarification of some construction work that locals had picked up on at the Wooreen Energy Storage System, a 350 megawatt (MW) battery with four hours of storage (1,400 MWh).

According to EnergyAustralia, “a few neighbours” recently got in touch to query the new “tall, shiny poles” being erected at Wooreen, concerned that the project would “be extra bright at night with lights that high”.

However, it turns out the poles aren’t primarily for lighting – though they will have lights equipped much lower to the ground – but are in fact for lightning.

The lightning rods will attract lightning away from the more sensitive equipment at the battery and “give it an easy, safe path into the site’s earthing grid, so it never goes near the equipment.”

“Lights will be fitted, but much lower down the pole, close to the batteries and inverters,” EnergyAustralia added. “That’s where our crews need to see, and it keeps the glow low and local.”

The Wooreen battery is being developed next door to EnergyAustralia’s existing Jeeralang gas power plant in the heart of Victorian coal country.

EnergyAustralia , one of Australia’s three biggest privately owned utilities, broke ground on the $700,000 million project in February of 2025, hailing it as “the biggest single investment ” the company has ever made.

In July, it sold a 50 per cent share in the WESS project to Banpu Energy Australia, the local subsidiary of the Thai energy giant, for about $110 million. EnergyAustralia is still building and operating the project, as well as leading community engagement.

EnergyAustralia says it has already responded directly to the few emails that came in asking about the lightning rods and is now sharing the information on its social media channels, before it also shares it in its upcoming community updates.

The WESS is scheduled for completion and commissioning in 2027.