Answers to questions on notice from Independent Yerrabi MLA Leanne Castley reveal the new timeline for Gungahlin East.

Gungahlin Community Council said the new delay was disappointing but was part of a pattern of government behaviour towards the town centre.

Ms Castley asked Chief Minister Andrew Barr whether the government had submitted a subdivision design application and, if not, why not and when it would.

She also wanted to know whether the government still expected to meet the milestones on the SLA website: subdivision approval in 2026, the start of civil works in 2027, and initial land release in 2027.

Mr Barr said the lead design consultant preparing the Subdivision Design Application (SDA) went bust recently, and a new consultant has been engaged.

He said the SDA was now expected to be lodged in the last quarter of 2026-27.

Subdivision approval was forecast to be completed in 2027-28, with civil works and land release expected in the same financial year.

Ms Castley said the delay would further hold up the delivery of new homes, businesses, and community spaces.

She said the revelation of more delays was just another example of Labor’s neglect of the north.

“Whether it’s their promises on housing, health, parks, police, or sports, the only thing Labor delivers are excuses,” Ms Castley said.

Only eight months earlier, on 25 March, Mr Barr told the Legislative Assembly that SDA had been finalised for lodgment in mid-2026, with staged land releases planned from fiscal 2026-27 onwards.

On 9 April 2024, then Minister Yvette Berry told the Assembly that land was expected to be released in the 2025-26 financial year.

Ms Castley said she had little faith in the government’s forecasts.

She said that after two years of work, the project was now two years behind schedule.

“It’s hard to believe they will complete the subdivision application, get through the approval process, complete all the civil works, and have the site ready for land release in just 18 months,” she said.

Ms Castley said Gungahlin residents were crying out for more local businesses, offices, jobs, and public spaces.

“Gungahlin Town Centre East was supposed to help deliver that but, once again, Labor has delivered nothing but delays and disappointment.

“It’s particularly disappointing this information wasn’t announced but had to be forced to be released.”

Ms Castley said the government’s June 2026 land-release program was already outdated.

She said the program committed to releasing two substantial sites, spanning residential and commercial use, in Gungahlin Town Centre East this financial year. These sites would now not be ready until 2027-28 or later.

The Gungahlin Community Council (GCC) said the latest unexplained two-year delay to land release in Gungahlin Town Centre East added to a pattern of slippage in the last major undeveloped part of the town centre.

President Henley Samuel said the government should say why the SDA was delayed.

He acknowledged the appetite for more housing but said Gungahlin East was where the government should make good its commitment for commercial and employment space in the town centre.

He said the 2010 Gungahlin Town Centre Planning Report reserved land for up to 200,000 square metres of commercial office space, enough for around 10,000 jobs, but that had since been halved to 100,000 square metres, and the methodology behind the reduction has been questioned by a Legislative Assembly committee.

“With around 65,000 square metres of that target still undelivered, the East precinct is where the commitment must be honoured,” Mr Samuel said.

“Each time the commercial floor space target has been reviewed, the area reserved has gone down. The pattern is clear, and it must stop with the last major precinct.”

Everything you need right at home. Now selling 2 & 3 bedroom residences above Taylor Town Centre.

Mr Samuel said the delay must be used get the detailed planning right, not to defer decisions until the land has been sold.

He said the GCC wanted the government to show how consultation was used and publish how each recommendation had been addressed in the final design and subdivision application, and explain where it has not.

Commercial land must be protected and the commercial office reservation kept at no less than 100,000 square metres.

Land in the east should be protected for large-scale office use through zoning and lease conditions and minimum non-residential floor areas set, especially on mixed use sites.

Mr Samuel said releases should be staged so commercial and community land was in step with residential land, not after it.

He said the analysis behind the commercial space target should be published abd be independently reviewed.

“Gungahlin residents have waited a long time for a town centre that serves them. Land sold for residential profit alone will not deliver one,” Mr Samuel said.

Gungahlin Town Centre East is a major expansion of the town centre, expected to deliver 2500 homes, including affordable and build-to-rent housing, alongside shops, offices, and community spaces.

The Design and Place Framework was the product of two years of community consultation.