The build-out of new transmission infrastructure across New South Wales has hit a pair of important milestones in the last week, with the 100 th transmission tower erected across the Central-West Orana Renewable Energy Zone (REZ) and construction on the HumeLink East project marking the one-year mark.
Spanish giant Acciona announced this week that 100 transmission towers had been installed for the Central-West Orana REZ it is developing as ACEREZ, a partnership with fellow Spanish infrastructure construction firm Grupo Cobra and Australian electrical distribution network operator Endeavour Energy.
The 100th tower was a 70-metre, 48-tonne double-circuit steel lattice tower which will support two independent 500 kV electrical circuits.
The Central-West Orana REZ was the first REZ formed in Australia and will eventually include 90 kilometres of 500 kV transmission lines and 150 kilometres of 330 kV transmission lines, connecting several renewable energy generation facilities to the state’s grid.
“This progress is really exciting and highlights how ACEREZ is getting on with the job of building crucial energy infrastructure across the Central-West Orana REZ,” said ACEREZ CEO Steve Masters .
“We have 100 towers raised, stringing is underway and work at our energy hubs is well advanced. We are focussed on building the infrastructure so we can start delivering clean, reliable energy to homes and businesses across the state from 2028.”
The news comes a week after Acciona announced that it had passed the one-year mark on construction of HumeLink East, one of the largest energy infrastructure initiatives in Australia comprising 225 km of 500 kV overhead transmission lines from Bannaby to Wondalga, and the upgrading of the 500 kV Bannaby substation.
HumeLink East is being delivered for network operator, Transgrid, by a joint venture between Acciona and local construction firm Genus. Once completed, HumeLink East and West will help to strengthen the New South Wales electricity grid, making it more reliable and sustainable and will unlock new capacity, including from the massive Snowy 2.0 project.
Acciona says the past 12 months of work on HumeLink East has included the construction of 382 tower pads and more than 70% of the foundations along the project’s 225km alignment.
A total of 157 transmission towers have also been installed, with the 200th expected to be built in the coming weeks.
Civil works on the expansion of the Bannaby 500kV substation are also nearing completion, with the commissioning of new electrical equipment already under way.
Acciona and Genus are also now moving on to stringing the more than 6,000 kilometres worth of conductor between the completed towers, utilising helicopters to string conductors.