New Pacific Metals (TSX: NUAG) (NYSE-A: NEWP) has released an updated preliminary economic assessment (PEA)for its Carangas project in Bolivia.
The updated Carangas PEA considers an increased throughput rate and the inclusion of the gold zone when compared to the previous PEA released in 2024.
The company said the project has robust economics, manageable upfront capex, annual silver production of approximately ten million ounces per year, and over one million ounces of gold produced over the life of mine.
The PEA reports post-tax net present value (NPV) of $65 billion and internal rate of return (IRR) of 35.9% at base case metal prices of: $45.00/oz silver, $3,400/oz gold, $1.20/lb) zinc and $0.90/lb lead.
Post tax NPV and IRR of $16 billion and 51.5%, respectively, at $67.50/oz silver and the other metal prices held constant; post tax NPV and IRR of $3.23 billion and 37.0%, respectively, at $5,100/oz gold and the other metal prices held constant.