She says it took Council less than three months to build Methvens Bridge.
‘All that remains to be done now is clean-up the site and remove the side track’.
‘In the meantime, the opening date for the new Montgomerys Bridge is still on track for the end of August, despite disruptions caused by the ongoing wet weather.
‘Work on the final abutment began this week, and once the final girders are installed the crew will start work constructing the deck insitu.
‘Piling works are progressing on the Clarks Lane footbridge, with all the pilings expected to be completed by the end of the week. The focus will then turn to concrete works.
‘Council recognises the impact the ongoing wet weather has had on its 700km gravel road network and how this effects residents. Council is doing all it can to maintain its unsealed roads, but the consistent rainfall has made this increasingly difficult.